City Announces Kegley Phase I Reconstruction Substantially Complete

Kegley Phase 1 - Detour


**UPDATE** TEMPLE, TX (October 24, 2018) – Kegley Phase I reconstruction is substantially complete and the road has been opened to through traffic. Staff is currently working to complete right-of-way acquisition and dry utility relocation for Phase II. Construction is currently scheduled to begin early summer 2019.

Updates on all TCIP projects are provided thru the city’s website at: www.templetx.gov/TCIP.